Building phases You decide for yourself which stage of construction you want the low-energy prefabricated house.

faze

Construction phases 1 and 2

• Setting up the construction site and the construction fence; Delivery and erection of the construction site board; Renting and setting up the construction site TOILET.
• Appointment of the responsible construction manager.
• Inspection of the floor slab and review of the construction protocol from the foundation phase.
• Taking over and reviewing the project to implement and inform all construction participants about safety work instructions and review the safety plan.
• Keeping a construction log of construction and craft work.
• Base plate design (optional).
• Sealing of the base plate (optional).

Construction phase 3

• Delivery and installation of the skeleton system for external and internal load-bearing and non-load-bearing walls as well as delivery and installation of fibreboard.
• Execution of vertical sealing of the external wall.
• Lathing the top of the ceiling above the ground floor, executing a wooden substructure and roof construction and erecting an aluminum substructure (ground floor house).
• Laying and executing a wooden mezzanine structure as well as erecting an aluminum substructure (mansard house).
• Roof construction according to static calculations with thermal insulation, aluminum substructure, vapor barrier and fireproof plasterboard; Roofing with airlift and all roofing and plumbing work.
• Execution of gables and chimney.

Construction phase 4

• Delivery and installation of the facade insulation, the facade system, the interior installation level, the plasterboard and creation of the substructure.
• Delivery and installation of sound insulation in the interior wall, fiberboard, plasterboard and construction of interior sanitary walls.
• Delivery and installation of thermal insulation, vapor barrier film and plasterboard for the ceiling above the ground floor or attic.
• Delivery and installation of construction furniture (windows, front doors, window sills, blinds).
• Flooring work on the ground floor and in the attic (mansard house) with underfloor heating.
• Delivery and installation of attic stairs (ground floor house).
• Electrical installation work rough.
• Mechanical installation work rough.
• Painting work – sealing.

Construction phase 5

• Painting work (sealing the joints and painting with white paint).
• Installation of floor and wall coverings (ceramic, vinyl, parquet).
• Supply and installation of sanitary facilities.
• Execution of the heating system and hot water preparation (electric boiler for low-temperature underfloor heating, electric water heater; option at extra cost – heat pump).
• Fine electrical installation work.
• Delivery and installation of interior doors with locks and handles.
• Delivery and installation of internal stairs and railings (mansard house).



Ask us!

If you did not find the desired information in the answers to frequently asked questions,
you can write to us or send us a form and we will be happy to answer all your questions about our service.

Question Frequently asked questions and answers

buiding phases

All materials used in the production process are the result of good development
cooperation with leading manufacturers of building materials.

Consult an experienced specialist  Contact us